Summary
Location: Kingston Street, Brigadoon Circuit and Oak Flats Dog Park, Oak Flats
Timeframe: Construction commencing Thursday 20 August 2026 for approximately 3-5 weeks, weather permitting
Construction Hours: 7am to 4pm, Monday to Friday
About the Project:
Shellharbour City Council is delivering a new footpath between Kingston Street and Brigadoon Circuit, Oak Flats, including new facilities within the Oak Flats Dog Park.
The project responds to community requests for improved pedestrian connectivity and enhanced amenities within the dog park.
These works will provide a safer and more convenient pedestrian connection while creating a more comfortable and welcoming space for dog park users.
Key features include:
- Construction of a new 1.5-metre-wide footpath between Kingston Street and Brigadoon Circuit
- Connection of the new footpath to the existing bridge crossing
- New connecting footpaths within the Oak Flats Dog Park
- Two new shade shelters
- New seating areas
- Sandstone blocks to enhance the park's amenity
- Improved accessibility and connectivity
During construction, the community may notice construction vehicles, machinery and workers operating on site between 7am and 4pm, Monday to Friday. Temporary fencing will be installed around active work areas to ensure community safety, and minor changes to pedestrian movements may be required near construction zones. Some sections of the dog park may be temporarily restricted while upgrades are undertaken, and construction materials and equipment may be stored within designated work areas.
The dog park will remain accessible during construction. One access gate to both the small and large dog areas will remain open at all times, allowing continued use of the facility while works are underway. Council will work to minimise disruptions and appreciate the community's patience while these improvements are delivered.
Timeline
Stage 1 - Footpath Connection
Construction of a new 1.5-metre-wide footpath between Kingston Street and Brigadoon Circuit, including connection to the existing bridge crossing.
Stage 2 - Dog Park Pathways and Foundations
Construction of new footpaths within the dog park and concrete slabs for the new shelters and seating.
Stage 3 - Shelter, Seating and Landscape Elements Installation
Installation of two new shade shelters and seating areas within the dog park. Installation of sandstone blocks to complement the upgraded facilities and enhance the usability of the space for park users.
Completion
Works are expected to be completed within approximately 3-5 weeks, weather permitting.
FAQs
Why is Council delivering this project?
Council is committed to improving safety, accessibility and connectivity across the city through active transport infrastructure. This project will provide a new pedestrian link between Kingston Street and Brigadoon Circuit while enhancing amenities within the Oak Flats Dog Park.
When will construction begin?
Construction is scheduled to commence on 20 August 2026 and is expected to take approximately 3-5 weeks, weather permitting.
What are the construction hours?
Construction will generally take place between 7am and 4pm, Monday to Friday.
Will the dog park remain open during construction?
Yes. The dog park will remain open during construction.
To allow works to be completed safely, some sections of the park may be temporarily fenced off or subject to changed access arrangements. However, one access gate to both the small and large dog areas will remain available at all times, allowing the community to continue using the facility throughout construction.
Will pedestrian access be affected?
Minor changes to pedestrian movements may be required around active work areas while the new footpaths are constructed. Signage will be installed to help guide park users safely around the site.
Will there be impacts for nearby residents?
Nearby residents may experience temporary construction noise, increased construction vehicle movements and general construction activity during approved work hours.
What happens if there is wet weather?
Construction timeframes may be affected by adverse weather conditions. Any significant changes to the schedule will be communicated via this webpage.