Summary

Location: Cove Boulevard and Harbour Boulevard, Shell Cove 

Timeframe: April 2026 to June 2026

About the Project

Council is making various road safety improvements along Cove Boulevard and Harbour Boulevard. 
 
The project includes:  

  • The installation of a roundabout at the existing T-intersection of Harbour Boulevard and Promontory Drive (north). 
  • Installation of a bike path along Cove Boulevard between Shellharbour Road & Harbour Boulevard. 
  • Construction of three new pedestrian crossings at the roundabout of Cove Boulevard and Southern Cross Boulevard
  • Construction two new pedestrian crossings along Harbour Boulevard near Brigantine Drive (Warrigal Shell Cove) and Aquatic Drive (93 Harbour Boulevard) 

These upgrades will improve safety for active transport users and drivers, make crossings and paths more accessible for pedestrians, and improve traffic flow at the intersection of Harbour Boulevard and The Promontory Drive (north). 

Timeline

Concept Designs – Completed 
Concept designs prepared 

Detailed Designs - Completed 
Detailed designs developed 

Tender – Commenced January 2026
The construction package was put out to tender in late January 2026, to appoint the works contractor by March 2026 

Construction – April 2026 to June 2026 
Works are planned to commence in early March 2026  

Completion – July 2026 
The project is expected to be completed by July 2026

FAQs

Why are these upgrades needed?

There is currently a missing connection between existing shared paths in Shell Cove, and limited safe crossing points on key roads. Once complete, there will be a cohesive east- 

west share path connecting Shellharbour Village, the Marina and Shellharbour Junction train station. These upgrades will: 

  • Improve safety for pedestrians, cyclists and drivers 
  • Provide safer road crossings and better accessibility 
  • Support Council’s Active Transport Strategy by improving walking and cycling connections 
  • ​​​​​​​Help improve traffic flow at busy intersections 

What works are included in the project?

The project is being delivered in two stages: 

Stage A1 – Cove Boulevard 

  • Construction of a new on-road cycle path linking Shellharbour Road and Harbour Boulevard
  • Renewed bus stops
  • Three new pedestrian crossings near Southern Cross Boulevard (Seascape Park)
  • Widened footpaths to create shared paths 


Stage A2 – Harbour Boulevard

  • A new roundabout at the Harbour Boulevard and Promontory Drive (north) intersection
  • A pedestrian crossing at the new roundabout
  • Two additional pedestrian crossings near Brigantine Drive and Aquatic Drive 

View the project plans here

When will construction start and finish?

  • Construction start: Late April/early May 2026
  • Expected completion: June–July 2026 

Timing may be adjusted due to weather or construction conditions, and updates will be provided on Council’s website. 

Will there be traffic delays during construction?

Yes. There will be temporary traffic changes, including:

  • Reduced speed limits
  • Lane closures
  • Traffic controllers at times
  • Some detours may occur

Council will aim to minimise disruption, and some works may take place at night where possible to reduce traffic impacts. 

 

Will access to homes and businesses be maintained?

Yes. Access to homes, businesses and emergency services will be maintained at all times. If temporary access changes are required, affected residents and businesses will be notified in advance. 

Is parking being removed?

Some on-street parking space will be removed along sections of Cove Boulevard, mainly where it is not considered functional parking. 
 
There are no significant impacts to parking around the Shell Cove Marina, and alternative parking options remain available in the surrounding area. 

Why is a bike lane being added?

The new bike lane on Cove Boulevard will close a long-standing gap between existing shared paths, creating a more connected and safer cycling network. This supports Council’s Active Transport Strategy and provides a safer option for people who already cycle in the area. Once complete, there will be a cohesive east-west share path connecting Shellharbour Village, the Marina and Shellharbour Junction train station.

Will cyclists be forced to use the new bike lane?

No. The bike lane provides a dedicated option for cyclists, but people can choose the route that suits them best. The aim is to improve safety and reduce conflict between road users. 

How will pedestrian safety improve?

The project includes: 

  • New pedestrian crossings at key locations
  • Improved accessibility, including kerb ramps
  • Traffic calming through the new roundabout and crossings 

These changes make it safer and easier to cross busy roads, particularly for families, older residents and people with mobility needs. 

How will the community be kept informed?

Council will provide regular updates through: 

  • The project webpage
  • Social media
  • On-site signage
  • Letters to nearby residents (where required) 

Who can I contact if I have questions or concerns?

If you have questions or would like more information, please contact: 

Infrastructure and Projects Administration 
infrastructureandprojectsadmin@shellharbour.nsw.gov.au 
02 4221 6111 

Contact Information

Have questions or want to learn more about a project, contact us below:
Name: 
Infrastructure and Projects Administration
Phone: 
4221 6111
Last updated : Thu 26 Mar 2026